The Zulu monarch has confided in the government of the the financial implication of his project.

An unfinished reed dance venue initiated by King Goodwill Zwelithini that has been plagued by cost overruns will end up with a price tag of R1-billion if completed.

The Department of Arts and Culture says the only other option is to demolish the cultural village at Enyokeni Palace in Nongoma, northern KwaZulu-Natal.

It faces the choice after a forensic accounting investigation commissioned by Arts and Culture Minister Nathi Mthethwa found that the final cost would be eight times the original budget.

“Two options discussed are the completion of [the cultural precinct] or demolishing the work done and restoring the site to its original state,” the department said in a report to the National Treasury, in which it asked for advice on how to proceed.

The Treasury responded only by saying that if the department went ahead, it must have a written agreement with the Zulu royal household or the Ingonyama Trust that they would maintain the new buildings.

Enyokeni Palace hosts the annual reed dance in September and Umkhosi Wokweshwama (first fruits ceremony) in early December.

The king requested construction of the cultural precinct in 2013, but Mthethwa halted work in 2016 and appointed Gobodo Forensic Investigative Accounting to probe allegations of wrongdoing and overcharging.

At the time, Mthethwa’s department had spent R129-million, and the Gobodo investigation revealed that R1-billion would be required to complete the project.

It found that prices had been inflated and consultants had charged up to 200% more than standard industry rates, and said:

 

  • One contractor received R11-million for items that had nothing to do with the reed-dance precinct;
  • A consultant inflated a statutory fee by R3-million;
  • A construction monitoring fee was inflated by R450,000; and
  • An engineering fee was overstated by R5-million. In total, R20-million had been paid to consultants by the time Mthethwa halted the project, and the Arts and Culture Department told the press this week the project remained on hold pending a decision on “the best implementation approach”.                                                                    Mthethwa’s spokeswoman, Asanda Magaqa, said a financial summary compiled by the implementing agent, the Independent Development Trust, while construction was still in progress showed, however, that only an estimated R18.1-million would be needed to complete the project. The department had budgeted R55.6-million for the project in 2018-19 but would be unable to estimate the total required until a “sound financial plan” was devised.